Fuselage
|
|
Page
2
|
|
|
Millions of jig blocks later...I'm
kidding, but there were a lot of them. I made the jig blocks drilled with
a countersunk drill bit to keep the screw heads below the level of the
spruce members. Ahh! the end of day one of actual building.
|
|

|
|
|
|
|
The next day, I finish cut
and fitted all the spruce for both sides. I epoxied everything with T-88.
After a few hours in the jig I pulled side one out. I put two bar clamps
on the longerons to prevent springback. On to the next side. Let them
set up overnight.
|
|

|
|
|
|
Here is the result. Two identical
sides hanging up on the wall. End of the second day of work.
|
|

|
|
|
|
|
| |
|
|
|
|
|